Indiana Utility Says AWS Investment Is Speeding Up Grid Upgrades
Indiana Michigan Power says the New Carlisle data-center project is helping it replace aging infrastructure faster. The utility's comments came at a regional economic event.

Indiana Michigan Power says investment tied to Amazon Web Services' data-center project in New Carlisle is allowing it to accelerate improvements to aging electrical infrastructure.
Jill Scicchitano, who works in economic and business development for the utility, made the comments during the South Bend Regional Chamber of Commerce's State of the Economy event Wednesday, according to WNDU.
She said the utility would not be able to rebuild and improve infrastructure that is 50 to 60 years old as quickly without the AWS project's investment. The statement describes the utility's assessment of the project, not a guarantee that every customer's bill will fall.
Power supply, jobs and wages were central topics at the event. Chamber President Jeff Rea said residents continue to have questions about water, electricity and the development's local impact, ABC57 reported.
AWS said it has invested more than $13.8 billion in its New Carlisle project since construction began in May 2024, according to WSBT. The company said 18 of 32 planned buildings are now vertical. That construction milestone does not mean all 18 are finished or operating.
The company reported more than 1,100 full-time workers and 400 construction workers at the project. WNDU reported that about half of the full-time jobs were held by St. Joseph County residents and about 80% by Indiana residents, according to figures presented at the event.
Those company figures and the utility's grid-upgrade assessment address parts of the project's economic impact. They do not settle the wider questions residents have raised about energy demand, water use and future development.